Emergency Migrations - S655 VPS Customers
Scheduled Maintenance Report for Crucial Hosting
Completed
The scheduled maintenance has been completed.
Posted May 20, 2016 - 09:11 AEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 10, 2016 - 10:00 AEST
Scheduled
Over the last month we have been experiencing hardware issues with the VPS Hypervisor S655. This has resulted in outages for a small number of Crucial VPS customers over the last 26 days. Please accept our sincerest apologies for these issues and trust that we are working hard to resolve them.

Our plan to ensure continued reliability for your server is to perform a complete hardware replacement onto a newly deployed VPS Hypervisor utilising high-performance Dell Hardware.

These migrations will be performed over the next 72 hours.
Posted May 09, 2016 - 15:21 AEST