GLSW to Equinix SY5 vps.crucial.com.au Migration

Scheduled Maintenance Report for Crucial Hosting

Completed

The scheduled maintenance has been completed.
Posted Nov 10, 2021 - 02:26 AEDT

Verifying

The servers are online and final checks are being run
Posted Nov 10, 2021 - 02:09 AEDT

Update

The servers are being unloaded and racked. Once online, we will be performing network and sanity checks.
Posted Nov 10, 2021 - 00:36 AEDT

Update

The servers are now en route to Equinix SY5. We will continue to provide updates as necessary.
Posted Nov 09, 2021 - 23:39 AEDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 09, 2021 - 22:00 AEDT

Scheduled

As part of our ongoing commitment to ensure all of our services are operating and maintained to our standards, Crucial will be migrating our vps.crucial.com.au control panel to the new, state of the art Equinix SY5 Data Centre.

This migration will commence at 10pm AEST, and is estimated to take up to 7 hours to complete.

Our teams always endeavour to minimise disruption to our customers. This should not impact your VPS service, just the control panel used to perform tasks like reboot, and shutdown during the maintenance.
Posted Nov 09, 2021 - 16:40 AEDT
This scheduled maintenance affected: Virtual Server Platform.